SITEWORK FOR 20 MW ILUMINA SOLAR FARM, GUAYAMA

CLIENT

AES Ilumina, LLC

Guayama

SCHEDULE

Started : OCTOBER 2011

Completed : FEBRUARY 2012

CONTRACT

US $ 2,221,000

(as Subcontractor of GES USA)

Project Summary

The project consisted of the clearing and grubbing of 430,000 square meters, 184,800 cubic meters of excavation activities, 5,300 meters of internal roads, drainage structures, sanitary pipe crossing, temporary erosion control, and other miscellaneous works.


The Scope

  • Clearing and grubbing operations in over 100 acres..
  • Excavation was originally estimated at 157,800 cubic meters. Due to redesign changes in ponds, the total excavation topped 184,800 cubic meters..
  • High traffic haul road construction and maintenance for 40-ton rigid frame highway trucks. This presented a challenge due to the excessive rains common to the area.
  • Excavation and fill of inverter pads.
  • Drainage structures.